OLEGIV Podil
Construction progress for November 2024

04.12.2024

Go back

In November 2024, the following works were performed at the construction site:

Section 1:

  • Concrete reinforcement of the structure on the roof of the elevator shaft and stairwell – 100%
  • Reinforcement of concreting of the floor slab of the 8th floor from +25.895 – 100%
  • Masonry of the external internal walls of partitions from the 1st to the 5th floor – 50%

Section 2:

  • Concrete reinforcement of the structure on the roof of the elevator shaft and stairwell – 100%
  • Masonry of the external internal walls of the partitions on the 3rd floor – 100%

Section 3:

  • Concrete reinforcement of the structure on the roof of the elevator shaft and stairwell – 100%
  • Masonry of external internal walls 3rd floor – 100%, 4th floor – 90%, 5th floor – 5%

Section 4:

  • Reinforcement of concreting of vertical structures, floor slabs, 8th floor – 100%

Section 5:

  • Concreting reinforcement of vertical structures 5th, 6th, 7th floor – 100%