Construction progress for July 2024
20.07.2024
Go back
The DIM company performs work at the construction site on the street. Olehivska, 36.
In July 2024 the following works were performed at the construction site:
Section 1:
- Reinforcement of concreting of vertical structures of floor slabs 1, 2 floors - 100%
Section 2:
- Masonry of partition walls 1st floor - 25%
- Reinforcement of concreting of the 5th floor - 48%
Section 3:
- Reinforcement of concreting of vertical structures of floor slabs 4, 5, 6 floors - 100%
- Masonry of partition walls 1st floor - 55%
Section 4:
- Reinforcement of concreting of vertical structures of floor slabs 3, 4 floors - 100%
- Concreting reinforcement of vertical structures 5th floor - 40%
- Masonry of partition walls 1st floor - 55%
Section 5:
- Concreting reinforcement of vertical structures of the lower part of the section - 100%