Construction progress for October 2024
04.11.2024
Go back
DIM company is performing work at the construction site on the street. Olegivska, 36.
In October 2024, the following works were performed at the construction site:
Section 1:
- Reinforcement of concreting of vertical structures from 7 to 8 floors and parapets - 100%
- Reinforcement of concreting of floor slabs from 6 to 7 floors - 100%
Section 2:
- Reinforcement of concreting of vertical structures of floor slabs 7, 8 floors, parapets and roof structures - 100%
- Masonry of external and internal walls of partitions 1, 2 floors - 100% and 3 floors - 60%
Section 3:
- Reinforcement of concreting of vertical structures of floor slabs 7, 8 floors, parapets and roof structures - 100%
- Masonry of external and internal walls of partitions 1, 2 floors - 100% and 3 floors - 80%
Section 4:
- Reinforcement of concreting of vertical structures, floor slabs 6, 7 floors – 100%
- Masonry of external and internal walls of partitions 1 floor – 100%
Section 5:
- Reinforcement of concreting of vertical structures 3, 4 floors – 100%