Construction progress for October 2024

04.11.2024

Go back
Хід будівництва Олегів Поділ

DIM company is performing work at the construction site on the street. Olegivska, 36.

In October 2024, the following works were performed at the construction site:

Section 1:

  • Reinforcement of concreting of vertical structures from 7 to 8 floors and parapets - 100%
  • Reinforcement of concreting of floor slabs from 6 to 7 floors - 100%

Section 2:

  • Reinforcement of concreting of vertical structures of floor slabs 7, 8 floors, parapets and roof structures - 100%
  • Masonry of external and internal walls of partitions 1, 2 floors - 100% and 3 floors - 60%

Section 3:

  • Reinforcement of concreting of vertical structures of floor slabs 7, 8 floors, parapets and roof structures - 100%
  • Masonry of external and internal walls of partitions 1, 2 floors - 100% and 3 floors - 80%

Section 4:

  • Reinforcement of concreting of vertical structures, floor slabs 6, 7 floors – 100%
  • Masonry of external and internal walls of partitions 1 floor – 100%

Section 5:

  • Reinforcement of concreting of vertical structures 3, 4 floors – 100%