Construction progress for March 2024
26.03.2024
Go back
The DIM company performs work at the construction site on the street. Olehivska, 36.
In March, the following works were performed at the construction site:
Section 2:
- Concrete reinforcement of vertical structures, floor slabs 1st, 2nd floor - 95%
Section 3:
- Reinforcement of concreting of vertical structures, floor slabs 1st, 2nd floor - 95%
Section 4:
- Reinforcement of vertical structures of the first floor - 55%