OLEGIV Podil
Construction progress for June 2024

24.06.2024

Go back

The DIM company performs work at the construction site at 36 Olehivska Street.

In June 2024, the following works were performed at the construction site:

Section 1:

  • Reinforcement of concreting of vertical structures up to -0.000 - 100%
  • Reinforcement of concreting of the floor slab, odm -0100 and structures - 90%

Section 2:

  • Reinforcement of concreting of 3, 4 floors and structures - 100%
  • Reinforcement of concreting of the 5th floor - 45%

Section 3:

  • Reinforcement of concreting of the 3rd floor - 100%
  • Reinforcement of concreting of the 4th floor - 45%

Section 4:

  • Reinforcement of concreting of vertical structures of the 2nd floor - 100%
  • Reinforcement of concreting of the 3rd floor and structures - 45%

Section 5:

  • Concreting reinforcement of vertical structures of the lower part of the section - 90%