Construction progress for April 2026
30.04.2026
Go back
Construction results for THE ONE in April 2026:
Main building:
- Reinforcement and concreting of vertical structures on the 7th floor – 100%;
- Reinforcement and concreting of the floor slab on the 7th floor – 100%;
- Reinforcement and concreting of vertical structures on the 8th floor – 100%;
- Reinforcement and concreting of the floor slab on the 8th floor – 100%;
- Reinforcement and concreting of vertical structures on the 9th floor – 45%;
- Installation of prefabricated reinforced concrete staircases and landings, 6-8 floors – 100%;
- Installation of ventilation blocks, 4-7 floors – 100%.
Left stylobate:
- Reinforcement and concreting of the floor slab on the -2 floor – 100%.
A total of 688 m³ of reinforced concrete frame structures were completed in April.