Construction results for THE ONE in April 2026:

Main building:

  • Reinforcement and concreting of vertical structures on the 7th floor – 100%;
  • Reinforcement and concreting of the floor slab on the 7th floor – 100%;
  • Reinforcement and concreting of vertical structures on the 8th floor – 100%;
  • Reinforcement and concreting of the floor slab on the 8th floor – 100%;
  • Reinforcement and concreting of vertical structures on the 9th floor – 45%;
  • Installation of prefabricated reinforced concrete staircases and landings, 6-8 floors – 100%;
  • Installation of ventilation blocks, 4-7 floors – 100%.

Left stylobate:

  • Reinforcement and concreting of the floor slab on the -2 floor – 100%.

A total of 688 m³ of reinforced concrete frame structures were completed in April.