Construction Progress for September 2026
01.10.2026
Go back
THE ONE Construction Progress — September 2026
Main building:
- reinforcement of vertical structures on the 18th floor — 100%
- concreting of vertical structures on the 18th floor — 100%
- reinforcement of the 18th-floor slab — 100%
- concreting of the 18th-floor slab — 100%
- reinforcement of vertical structures on the 19th floor — 100%
- concreting of vertical structures on the 19th floor — 100%
- reinforcement of the 19th-floor slab — 100%
- concreting of the 19th-floor slab — 70%
- reinforcement of vertical structures on the 20th floor — 50%
- concreting of vertical structures on the 18th floor — 50%
- installation of precast reinforced concrete stair flights and landings on floors 17–19 — 100%
- installation of ventilation blocks on floors 16–18 — 100%
Left stylobate: no changes Right stylobate: no changes
In September, 613 m³ of reinforced concrete structures for the building frame were completed.