Construction Progress for June 2026
01.07.2026
Go back
We're sharing the latest construction updates for June:
Building 4, Section 1:
- Installation of porcelain stoneware flooring in the basement common areas (common-use areas);
- Installation of electrical panels in apartments completed; electricity meters are being installed;
- Installation of glass façades – 72 sq m.
Building 4, Section 2:
Façade installation – 250 sq m.
Building 4, Section 3:
- Decorative plaster application in the common areas on the 11th floor;
- Apartment electrical panel installation – 50% complete;
- Underground waste container system installed near Building 4.
Building 6, Section 1:
- Heating pipe installation completed on the first two floors;
- Floor screed completed on the first two floors.
Building 6, Section 2:
- Façade works: brackets for balcony basket mounts completed;
- Thermal insulation – 80 sq m;
- Reinforcement layer – 450 sq m;
- Decorative finish and painting – 150 sq m.
Building 5, Section 3:
- Window installation: structures delivered; installation of window frames underway on the 3rd floor. Inner Courtyard:
- Installation of the construction site fence separating the landscaping area near Building 3;
- Preparatory works for finishing Transformer Substation TP5;
- Reinforcement completed; formwork installation in progress;
- Landscaping of the inner courtyard near the building is 80% complete, including the installation of an automatic irrigation system.