Lucky Land
Construction Progress for June 2026

01.07.2026

Go back

We're sharing the latest construction updates for June:

Building 4, Section 1:

  • Installation of porcelain stoneware flooring in the basement common areas (common-use areas);
  • Installation of electrical panels in apartments completed; electricity meters are being installed;
  • Installation of glass façades – 72 sq m.

Building 4, Section 2:

    Façade installation – 250 sq m.

Building 4, Section 3:

  • Decorative plaster application in the common areas on the 11th floor;
  • Apartment electrical panel installation – 50% complete;
  • Underground waste container system installed near Building 4.

Building 6, Section 1:

  • Heating pipe installation completed on the first two floors;
  • Floor screed completed on the first two floors.

Building 6, Section 2:

  • Façade works: brackets for balcony basket mounts completed;
  • Thermal insulation – 80 sq m;
  • Reinforcement layer – 450 sq m;
  • Decorative finish and painting – 150 sq m.

Building 5, Section 3:

  • Window installation: structures delivered; installation of window frames underway on the 3rd floor. Inner Courtyard:
  • Installation of the construction site fence separating the landscaping area near Building 3;
  • Preparatory works for finishing Transformer Substation TP5;
  • Reinforcement completed; formwork installation in progress;
  • Landscaping of the inner courtyard near the building is 80% complete, including the installation of an automatic irrigation system.