Construction Progress — September 2026

01.10.2026

Go back

Sharing the latest construction site updates for September:

Building No. 4, Section 1:

  • Porcelain stoneware flooring in the lobby has been completed;

  • Porcelain stoneware wall finishing in the lobby is in progress;

  • Installation of plasterboard ceilings has been completed;

  • Wall finishing in the common areas on the 2nd floor is in progress;

  • Façade works are 95% complete.

Building No. 4, Section 2:

  • Wall finishing in the common areas on the residential floors has been completed;

  • Façade works in the stairwell and elevator areas are 95% complete.

Building No. 4, Section 3:

  • Porcelain stoneware wall finishing in the lobby is in progress;

  • Installation of plasterboard ceilings has been completed;

  • Façade works on the electrical substation premises are 75% complete;

  • Landscaping works have commenced.

Building No. 6, Section 1:

  • Façade works are ongoing;

  • Thermal insulation is 100% complete;

  • Textured finish application is 75% complete;

  • Clinker-style painting is 35% complete;

  • Masonry works on the ground floor have been completed;

  • Brickwork is 95% complete.

Building No. 6, Section 2:

  • Installation of doors in the unheated passageways is 80% complete;

  • Floor screed has been completed from the 3rd to the 12th floor;

  • Protective cappings have been installed on the roof parapets and rooftop technical premises;

  • Masonry works on the ground floor are 90% complete.

Building No. 5, Section 3:

  • Window installation from the 3rd to the 8th floor is 100% complete;

  • Window installation from the 9th to the 13th floor is 50% complete.

Courtyard:

  • Installation of external water supply and sewerage networks for Building No. 6 has commenced. Sewerage outlets for Section 6.2 have been completed.

Children’s Playground:

  • Soil backfilling between the retaining walls has been completed, tunnels have been installed, and preparatory works for the installation of playground structures have been carried out.