Construction Progress — September 2026
01.10.2026
Sharing the latest construction site updates for September:
Building No. 4, Section 1:
Porcelain stoneware flooring in the lobby has been completed;
Porcelain stoneware wall finishing in the lobby is in progress;
Installation of plasterboard ceilings has been completed;
Wall finishing in the common areas on the 2nd floor is in progress;
Façade works are 95% complete.
Building No. 4, Section 2:
Wall finishing in the common areas on the residential floors has been completed;
Façade works in the stairwell and elevator areas are 95% complete.
Building No. 4, Section 3:
Porcelain stoneware wall finishing in the lobby is in progress;
Installation of plasterboard ceilings has been completed;
Façade works on the electrical substation premises are 75% complete;
Landscaping works have commenced.
Building No. 6, Section 1:
Façade works are ongoing;
Thermal insulation is 100% complete;
Textured finish application is 75% complete;
Clinker-style painting is 35% complete;
Masonry works on the ground floor have been completed;
Brickwork is 95% complete.
Building No. 6, Section 2:
Installation of doors in the unheated passageways is 80% complete;
Floor screed has been completed from the 3rd to the 12th floor;
Protective cappings have been installed on the roof parapets and rooftop technical premises;
Masonry works on the ground floor are 90% complete.
Building No. 5, Section 3:
Window installation from the 3rd to the 8th floor is 100% complete;
Window installation from the 9th to the 13th floor is 50% complete.
Courtyard:
Installation of external water supply and sewerage networks for Building No. 6 has commenced. Sewerage outlets for Section 6.2 have been completed.
Children’s Playground:
Soil backfilling between the retaining walls has been completed, tunnels have been installed, and preparatory works for the installation of playground structures have been carried out.