Construction progress for November 2024
06.12.2024
Go back
We share the latest news from the construction site for November:
Building No. 3 parking lot:
- arrangement of polymer coating of the parking lot floors.
Building No. 3, landscaping:
- arrangement of improvement of the inner yard.
House No. 4:
- arrangement of external power supply networks;
- installation of smoke removal and parking ventilation systems;
- improvement works have started;
- arranging the equipment of technical premises (floor screed; plastering).;
- arrangement of the roof of the parking lot of the outer and inner yard.
Building No. 4, Section 1:
- arrangement of MZK equipment from the 7th to the 13th floor (floor tiles, plastering of walls);
- decoration of LMM facades;
- arrangement of monolithic structures of stylobates under SPOK;
- installation of translucent fencing structures (SPOK);
- work continues on the arrangement of masonry on the 1st and 2nd floors;
- installation of smoke removal and ventilation systems;
- plastering of technical premises.
Building No. 4, Section 2:
- decoration of LMM facades;
- installation of ceramic tiles in MZK on floors 6-13;
- arrangement of masonry on the 1st and 2nd floors;
- installation of smoke removal and ventilation systems;
- installation of translucent fencing structures (SPOK);
- installation of PVC structures on cold passages, vestibules of the MZK;
- arrangement of the roof of the parking lot;
- installation of fire protection systems 3-13 floors.
Building No. 4, Section 3:
- arrangement of screeds of MZK 7-13 floors;
- arrangement of monolithic structures of stylobates under SPOK;
- arrangement of vertical waterproofing of monolithic structures of stylobates;
- installation of smoke removal and ventilation systems;
- installation of a lightning protection system;
- installation of PVC structures on cold passages, vestibules of the MZK;
- installation of ceramic tiles in MZK on floors 3-7;
- plastering of the walls of MZK 8-13 floors;
- plastering of technical premises.
Building No. 5, Section 1:
- construction of walls and partitions on the 10th floor continues;
- installation of staircases and platforms 12-13 floors.
Building No. 5, Section 2:
- construction of walls and partitions on the 10th floor continues.
Building No. 5, Section 3:
- arrangement of vertical and horizontal elements of the monolithic frame on the 12th floor;
- installation of ventilation units 8, 9 floors;
- arrangement of walls and partitions on the 4th floor.
Building No. 5, parking lot 1.6 (parking lot adjacent to section 3):
- arrangement of vertical elements of the monolithic frame on the 1st floor;
- arrangement of the roof, slope-forming screed;
- noise protection and decoration of TP.
Building No. 5, 1.5 (parking adjacent to sections 1-2):
- arrangement of horizontal elements of the monolithic frame - 1st floor.
Building No. 6, Section 1:
- work on glazing windows continues;
- arrangement of walls and partitions in the basement;
- installation of vertical transport (cargo elevator);
- installation of metal-plastic structures of windows 4, 5 floors.
Building No. 6, Section 2:
- preparatory work for the start of facade work (installation of fasteners and cradles);
- arrangement of walls and partitions in the basement;
- installation of vertical transport (cargo elevator).