Lucky Land
Construction progress for November 2024

06.12.2024

Go back

We share the latest news from the construction site for November:

Building No. 3 parking lot:

  • arrangement of polymer coating of the parking lot floors.

Building No. 3, landscaping:

  • arrangement of improvement of the inner yard.

House No. 4:

  • arrangement of external power supply networks;
  • installation of smoke removal and parking ventilation systems;
  • improvement works have started;
  • arranging the equipment of technical premises (floor screed; plastering).;
  • arrangement of the roof of the parking lot of the outer and inner yard.

Building No. 4, Section 1:

  • arrangement of MZK equipment from the 7th to the 13th floor (floor tiles, plastering of walls);
  • decoration of LMM facades;
  • arrangement of monolithic structures of stylobates under SPOK;
  • installation of translucent fencing structures (SPOK);
  • work continues on the arrangement of masonry on the 1st and 2nd floors;
  • installation of smoke removal and ventilation systems;
  • plastering of technical premises.

Building No. 4, Section 2:

  • decoration of LMM facades;
  • installation of ceramic tiles in MZK on floors 6-13;
  • arrangement of masonry on the 1st and 2nd floors;
  • installation of smoke removal and ventilation systems;
  • installation of translucent fencing structures (SPOK);
  • installation of PVC structures on cold passages, vestibules of the MZK;
  • arrangement of the roof of the parking lot;
  • installation of fire protection systems 3-13 floors.

Building No. 4, Section 3:

  • arrangement of screeds of MZK 7-13 floors;
  • arrangement of monolithic structures of stylobates under SPOK;
  • arrangement of vertical waterproofing of monolithic structures of stylobates;
  • installation of smoke removal and ventilation systems;
  • installation of a lightning protection system;
  • installation of PVC structures on cold passages, vestibules of the MZK;
  • installation of ceramic tiles in MZK on floors 3-7;
  • plastering of the walls of MZK 8-13 floors;
  • plastering of technical premises.

Building No. 5, Section 1:

  • construction of walls and partitions on the 10th floor continues;
  • installation of staircases and platforms 12-13 floors.

Building No. 5, Section 2:

  • construction of walls and partitions on the 10th floor continues.

Building No. 5, Section 3:

  • arrangement of vertical and horizontal elements of the monolithic frame on the 12th floor;
  • installation of ventilation units 8, 9 floors;
  • arrangement of walls and partitions on the 4th floor.

Building No. 5, parking lot 1.6 (parking lot adjacent to section 3):

  • arrangement of vertical elements of the monolithic frame on the 1st floor;
  • arrangement of the roof, slope-forming screed;
  • noise protection and decoration of TP.

Building No. 5, 1.5 (parking adjacent to sections 1-2):

  • arrangement of horizontal elements of the monolithic frame - 1st floor.

Building No. 6, Section 1:

  • work on glazing windows continues;
  • arrangement of walls and partitions in the basement;
  • installation of vertical transport (cargo elevator);
  • installation of metal-plastic structures of windows 4, 5 floors.

Building No. 6, Section 2:

  • preparatory work for the start of facade work (installation of fasteners and cradles);
  • arrangement of walls and partitions in the basement;
  • installation of vertical transport (cargo elevator).