Lucky Land
Construction progress for July 2024

20.07.2024

Go back

LUCKY LAND by DIM is under construction.

We share the latest news from the construction site for July:

Building No. 3, landscaping:

  • works on installing outdoor lighting continue;
  • landscaping of the territory continues;
  • improvement works (bicycle path) continue.

Building No. 4, Section 1:

  • installation of risers K1, K2 B1, B2 and air conditioner drainage risers;
  • installation of screeds in apartments and MZK from the 9th to the 13th floor;
  • plastering of common areas 4, 6, 7, 8, 9 floors;
  • arrangement of risers and apartment wiring of EO systems;
  • waterproofing of the terraces on the 3rd and 9th floors continues;
  • installation of elevator equipment;
  • decoration of facades;
  • arrangement of monolithic structures under SPOK.

Building No. 4, Section 2:

  • installation of risers K1, K2 B1, B2 and air conditioner drainage risers;
  • work continues on the installation of the screed in the apartments and MZK from the 9th to the 13th floor;
  • arrangement of risers and apartment wiring of EO systems;
  • waterproofing of the terraces on the 3rd and 9th floors continues;
  • installation of elevator equipment;
  • decoration of facades;
  • arrangement of monolithic structures under SPOK.

Building No. 4, Section 3:

  • installation of risers K1, K2 B1, B2 and air conditioner drainage risers;
  • arrangement of facades;
  • work is being carried out on the arrangement of the decoration of technical superstructures and ventilation shafts on the roof;
  • installation of elevator equipment;
  • work continues on the arrangement of waterproofing the terraces on the 3rd floor;
  • preparatory work for the installation of apartment networks of heating, water supply and electricity supply from the 3rd to the 13th floor;
  • preparatory work for the installation of the screed from the 3rd to the 13th floor;
  • arrangement of monolithic structures under SPOK.

Building No. 4, external networks:

  • arrangement of external power supply networks.

Building No. 5, Section 1:

  • arrangement of vertical and horizontal elements of the monolithic frame on the 12th floor;
  • arrangement of walls and partitions 5, 9 floors;
  • installation of ventilation units on the 9th and 10th floors;
  • installation of staircases and landings on the 10th and 11th floors.

Building No. 5, Section 2:

  • arrangement of vertical and horizontal elements of the monolithic frame on the 11th floor;
  • construction of walls and partitions continues on floors 5 and 9;
  • installation of ventilation units on the 9th and 10th floors;
  • the installation of staircases and landings on the 9th floor continues.

Building No. 5, Section 3:

  • arrangement of vertical and horizontal elements of monolithic frame 7, 8 floors;
  • installation of staircases and platforms 5, 6, 7 floors;
  • installation of vertical waterproofing;
  • installation of ventilation units on the 3rd and 4th floors continues.

Building No. 5, parking lot 1.6 (parking lot adjacent to section 3):

  • installation of a monolithic ramp slab;
  • arrangement of monolithic parapets;
  • work on installation of vertical waterproofing continues;
  • backfilling of the underground part;
  • arrangement of TP walls from solid bricks.

Building No. 5, parking lot 1.5 (the parking lot is adjacent to section 1-2):

  • work continues on the installation of vertical elements of the monolithic frame.

Building No. 6, Section 1:

  • work on the installation of walls and partitions in the basement (-1st floor) continues.

Building No. 6, Section 2:

  • work continues on the installation of walls and partitions in the basement (-1st floor);
  • preparation of elevator shafts for installation of elevators, grinding.