Construction progress for July 2024
20.07.2024
Go back
LUCKY LAND by DIM is under construction.
We share the latest news from the construction site for July:
Building No. 3, landscaping:
- works on installing outdoor lighting continue;
- landscaping of the territory continues;
- improvement works (bicycle path) continue.
Building No. 4, Section 1:
- installation of risers K1, K2 B1, B2 and air conditioner drainage risers;
- installation of screeds in apartments and MZK from the 9th to the 13th floor;
- plastering of common areas 4, 6, 7, 8, 9 floors;
- arrangement of risers and apartment wiring of EO systems;
- waterproofing of the terraces on the 3rd and 9th floors continues;
- installation of elevator equipment;
- decoration of facades;
- arrangement of monolithic structures under SPOK.
Building No. 4, Section 2:
- installation of risers K1, K2 B1, B2 and air conditioner drainage risers;
- work continues on the installation of the screed in the apartments and MZK from the 9th to the 13th floor;
- arrangement of risers and apartment wiring of EO systems;
- waterproofing of the terraces on the 3rd and 9th floors continues;
- installation of elevator equipment;
- decoration of facades;
- arrangement of monolithic structures under SPOK.
Building No. 4, Section 3:
- installation of risers K1, K2 B1, B2 and air conditioner drainage risers;
- arrangement of facades;
- work is being carried out on the arrangement of the decoration of technical superstructures and ventilation shafts on the roof;
- installation of elevator equipment;
- work continues on the arrangement of waterproofing the terraces on the 3rd floor;
- preparatory work for the installation of apartment networks of heating, water supply and electricity supply from the 3rd to the 13th floor;
- preparatory work for the installation of the screed from the 3rd to the 13th floor;
- arrangement of monolithic structures under SPOK.
Building No. 4, external networks:
- arrangement of external power supply networks.
Building No. 5, Section 1:
- arrangement of vertical and horizontal elements of the monolithic frame on the 12th floor;
- arrangement of walls and partitions 5, 9 floors;
- installation of ventilation units on the 9th and 10th floors;
- installation of staircases and landings on the 10th and 11th floors.
Building No. 5, Section 2:
- arrangement of vertical and horizontal elements of the monolithic frame on the 11th floor;
- construction of walls and partitions continues on floors 5 and 9;
- installation of ventilation units on the 9th and 10th floors;
- the installation of staircases and landings on the 9th floor continues.
Building No. 5, Section 3:
- arrangement of vertical and horizontal elements of monolithic frame 7, 8 floors;
- installation of staircases and platforms 5, 6, 7 floors;
- installation of vertical waterproofing;
- installation of ventilation units on the 3rd and 4th floors continues.
Building No. 5, parking lot 1.6 (parking lot adjacent to section 3):
- installation of a monolithic ramp slab;
- arrangement of monolithic parapets;
- work on installation of vertical waterproofing continues;
- backfilling of the underground part;
- arrangement of TP walls from solid bricks.
Building No. 5, parking lot 1.5 (the parking lot is adjacent to section 1-2):
- work continues on the installation of vertical elements of the monolithic frame.
Building No. 6, Section 1:
- work on the installation of walls and partitions in the basement (-1st floor) continues.
Building No. 6, Section 2:
- work continues on the installation of walls and partitions in the basement (-1st floor);
- preparation of elevator shafts for installation of elevators, grinding.