Construction progress for May 2025
04.06.2025
Go back
Construction results of THE ONE for May 2025:
Upper left part of the stylobate:
- fencing installation - 100%
- reinforcement of vertical structures - 5th floor - 100%
- concreting of vertical structures - 5th floor - 100%
- installation of bentonite mats on vertical surface - 5th floor - 100%
- installation of hydroexpansion at cold joints - 5th floor - 100%
- reinforcement of slab - 4th floor - 100%
- concreting of slab - 4th floor - 100%
- reinforcement of vertical structures - 4th floor - 100%
- concreting of vertical structures - 4th floor - 100%
- installation of bentonite mats on vertical surface - 4th floor - 100%
- installation of hydroexpansion at cold joints - 4th floor - 100%
Upper right part of the stylobate:
- installation of bentonite mats on vertical surface - 100%
- installation of hydroexpansion at cold joints - 100%
- installation of formwork for slab - 2nd floor - 100%
- reinforcement of slab - 2nd floor - 100%
- concreting of slab - 2nd floor - 100%
- reinforcement of vertical elements - 2nd floor - 100%
- concreting of vertical elements - 2nd floor - 100%
Main building:
- concrete preparation - 100%
- installation of bentonite mats on horizontal surfaces - 100%
- installation of hydroexpansion at cold joints - 100%
- installation of bentonite mats on vertical surface - 100%
- reinforcement of foundation slab - 100%
- concreting of foundation slab - 100%
- reinforcement of vertical structures - 6th floor - 30%
- concreting of vertical structures - 30%
- installation of sheet piling around excavation - 100%
- poured in May month - 1669.3 m3 of concrete