Construction results of THE ONE for May 2025:

Upper left part of the stylobate:

  • fencing installation - 100%
  • reinforcement of vertical structures - 5th floor - 100%
  • concreting of vertical structures - 5th floor - 100%
  • installation of bentonite mats on vertical surface - 5th floor - 100%
  • installation of hydroexpansion at cold joints - 5th floor - 100%
  • reinforcement of slab - 4th floor - 100%
  • concreting of slab - 4th floor - 100%
  • reinforcement of vertical structures - 4th floor - 100%
  • concreting of vertical structures - 4th floor - 100%
  • installation of bentonite mats on vertical surface - 4th floor - 100%
  • installation of hydroexpansion at cold joints - 4th floor - 100%

Upper right part of the stylobate:

  • installation of bentonite mats on vertical surface - 100%
  • installation of hydroexpansion at cold joints - 100%
  • installation of formwork for slab - 2nd floor - 100%
  • reinforcement of slab - 2nd floor - 100%
  • concreting of slab - 2nd floor - 100%
  • reinforcement of vertical elements - 2nd floor - 100%
  • concreting of vertical elements - 2nd floor - 100%

Main building:

  • concrete preparation - 100%
  • installation of bentonite mats on horizontal surfaces - 100%
  • installation of hydroexpansion at cold joints - 100%
  • installation of bentonite mats on vertical surface - 100%
  • reinforcement of foundation slab - 100%
  • concreting of foundation slab - 100%
  • reinforcement of vertical structures - 6th floor - 30%
  • concreting of vertical structures - 30%
  • installation of sheet piling around excavation - 100%
  • poured in May month - 1669.3 m3 of concrete