Construction progress for June 2025
01.07.2025
Go back
Construction results of THE ONE for June 2025:
Upper left part of the stylobate:
- Reinforcement and concreting of vertical structures -3rd floor - 50%
Main building:
- Reinforcement and concreting of vertical structures -6th floor - 100%
- Installation of bentonite mats on the vertical surface -6th floor - 100%
- Installation of hydroseeding on cold joints -6th floor - 100%
- Reinforcement and concreting of floor slab -6th floor - 100%
- Reinforcement and concreting of vertical structures -5th floor - 50%
- Completed in June - 498 m3 of reinforced concrete building frame structures.