Construction progress for June 2025

01.07.2025

Go back

Construction results of THE ONE for June 2025:

Upper left part of the stylobate:

  • Reinforcement and concreting of vertical structures -3rd floor - 50%

Main building:

  • Reinforcement and concreting of vertical structures -6th floor - 100%
  • Installation of bentonite mats on the vertical surface -6th floor - 100%
  • Installation of hydroseeding on cold joints -6th floor - 100%
  • Reinforcement and concreting of floor slab -6th floor - 100%
  • Reinforcement and concreting of vertical structures -5th floor - 50%
  • Completed in June - 498 m3 of reinforced concrete building frame structures.