Construction progress for July 2025

02.08.2025

Go back

Construction results of THE ONE for July 2025:

Main building:

  • Reinforcement and concreting of vertical structures -5th floor – 100%
  • Installation of bentonite mats on the vertical surface -5th floor – 100%
  • Installation of hydro expansion joint on the cold joints -5th floor – 100%
  • Reinforcement and concreting of slab -5th floor – 100%
  • Reinforcement and concreting of vertical structures -4th floor – 70%
  • Reinforcement and concreting of slab -4th floor – 50%
  • Completed for the month of June – 401 m3 of reinforced concrete structures of the building frame.