Construction progress for June 2026
01.07.2026
Go back
We are sharing the latest construction progress report for June:
VITA Quarter, Phase 1 Building No. 1.4
- Open-type garages — 75%
Building No. 1.5
- HVAC and water supply/sewer systems installation — 100% Landscaping works — 65% Electrical systems installation — 95% Wall and ceiling puttying — 100% Low-voltage systems installation — 95% Paving stone installation — 70%
VITA Quarter, Phase 2
Building No. 2.3
- HVAC and water supply/sewer systems installation — 15% Electrical installation works — 15% Video surveillance system installation — 10% Masonry works — 80%
Building No. 2.4
- HVAC and water supply/sewer systems installation — 45% Exterior lighting installation — 85% Electrical installation works — 50% Video surveillance system installation — 10%
Building No. 2.5
- Roof installation – 70% Facade works – 10% Exterior building lighting – 5%
Building No. 2.6
- Facade works – 14%
Building No. 2.8
- Internal brick masonry – 65%
Building No. 2.9
- Ground leveling to design elevation — 80%
AQUA Quarter
- Building No. 1.1 Roof installation – 100% Building glazing – 70%
Building No. 1.3
- Window glazing — 30%
Building No. 1.4
- Monolithic concrete works — 35%