Park Lake City
Construction progress for June 2026

01.07.2026

Go back

We are sharing the latest construction progress report for June:

VITA Quarter, Phase 1 Building No. 1.4

  • Open-type garages — 75%

Building No. 1.5

  • HVAC and water supply/sewer systems installation — 100% Landscaping works — 65% Electrical systems installation — 95% Wall and ceiling puttying — 100% Low-voltage systems installation — 95% Paving stone installation — 70%

VITA Quarter, Phase 2

Building No. 2.3

  • HVAC and water supply/sewer systems installation — 15% Electrical installation works — 15% Video surveillance system installation — 10% Masonry works — 80%

Building No. 2.4

  • HVAC and water supply/sewer systems installation — 45% Exterior lighting installation — 85% Electrical installation works — 50% Video surveillance system installation — 10%

Building No. 2.5

  • Roof installation – 70% Facade works – 10% Exterior building lighting – 5%

Building No. 2.6

  • Facade works – 14%

Building No. 2.8

  • Internal brick masonry – 65%

Building No. 2.9

  • Ground leveling to design elevation — 80%

AQUA Quarter

  • Building No. 1.1 Roof installation – 100% Building glazing – 70%

Building No. 1.3

  • Window glazing — 30%

Building No. 1.4

  • Monolithic concrete works — 35%