Sharing a fresh construction report for July:

VITA Quarter, Phase 1

House №1.5:

  • floor screeding - 2%

VITA Quarter, Phase 2

House №2.2:

    installation of ventilation and air conditioning - 80%

  • installation of heating system - 70%
  • interior finishing of the house - 65%
  • installation of doors in apartments - 85%
  • electric power installation in the building - 90%
  • installation of external networks - 50%
  • balcony and terrace glazing - 80%
  • low-current network installation - 60%
  • automatic irrigation system installation - 50%
  • lightning protection installation - 70%

House №2.3:

  • installation of external lighting - 90%
  • balcony screeding - 70%

House №2.7:

  • insulation of the basement - 100%

House №2.9:

  • ground elevation to the project mark - 65%
  • brick masonry installation - 5%

Local sewage treatment facilities:

  • foundation construction - 100%
  • facade installation - 100%
  • equipment installation - 60%