Construction progress for July 2025
02.08.2025
Go back
Sharing a fresh construction report for July:
VITA Quarter, Phase 1
House №1.5:
- floor screeding - 2%
VITA Quarter, Phase 2
House №2.2:
- installation of heating system - 70%
- interior finishing of the house - 65%
- installation of doors in apartments - 85%
- electric power installation in the building - 90%
- installation of external networks - 50%
- balcony and terrace glazing - 80%
- low-current network installation - 60%
- automatic irrigation system installation - 50%
- lightning protection installation - 70%
installation of ventilation and air conditioning - 80%
House №2.3:
- installation of external lighting - 90%
- balcony screeding - 70%
House №2.7:
- insulation of the basement - 100%
House №2.9:
- ground elevation to the project mark - 65%
- brick masonry installation - 5%
Local sewage treatment facilities:
- foundation construction - 100%
- facade installation - 100%
- equipment installation - 60%