Construction progress for June 2023
21.06.2023
PARK LAKE CITY by DIM is under construction. We share the latest news from the construction site.
PARK LAKE CITY – a business-class suburban eco-complex from DIM is actively being built. New houses are growing, new trees are being planted.
We share detailed construction news for June:
VITA Quarter, first phase
House No. 1.5:
Basement insulation – 50%
Window installation – 35%
Soil replacement for terraces, entrance groups and parking – 100%
Installation of cables according to the permanent power supply scheme – 70%
Exterior lighting of the house – 10%
Arrangement of the beach area:
Planting perennials – 90%
Installation of a volleyball court – 100%
VITA quarter, second line
House No. 2.1:
Facade lighting installation – 98%
Porch installation – 100%
Retaining wall installation – 95%
Installation of internal waterproofing of the house – 100%
Sand filling of the first floor – 63%
House No. 2.2:
Facade lighting installation – 99%
House No. 2.3:
Installation of geothermal wells for heat pumps – 95%
Elevator installation – 100%
House No. 2.4:
Facade installation – 17%
House No. 2.5:
Basement waterproofing – 100%
Installation of mortgages under K14 – 100%
Window installation – 20%
House No. 2.6:
Monolith installation – 85%