OLEGIV Podil
Construction progress for April 2025

02.05.2025

Go back

In April 2025, the following works were carried out at the construction site:

Section 1:

  • Masonry of external and internal partition walls 1st floor - 90%, 3rd floor - 80%, 5th floor - 80%

Section 3:

  • Masonry of external and internal walls 8th floor - 95%
  • Installation of windows from 1st to 8th floor - 95%
  • Installation of engineering systems, sewage and rainwater drainage has begun

Section 4:

  • Masonry of external and internal walls 5th floor - 75%, 6th floor - 80%

Section 5:

  • Masonry of external and internal walls 5th floor - 75%, 6th floor - 80%
  • Installation of windows from 1st to 7th floor - 95%, 8th floor - 75%

Parking 1 zone:

  • Arrangement of parking cover slab elevation -0.850 - 80%