OLEGIV Podil
Construction progress for July 2023

20.07.2023

Go back

OLEGIV PODIL by DIM is gaining momentum in construction! A new club house in Podil with incredible views of the city panorama.

In July, the following works were performed at the construction site:

Section 3:

  • Reinforcement of concreting monolithic grid 4.1 - 95%

  • Reinforcement of concreting monolithic grid 3.1 - 95%

  • Reinforcement of concreting monolithic grid 4.2 - 95%

  • Reinforcement of concreting monolithic grid 4.3 - 95%

  • Waterproofing of grills 4.1, 4.2, 4.3, 3.1 – 100%

Section 4:

  • Reinforcement of concreting monolithic grid 1 - 80%

  • Reinforcement of growing piles - 90%

  • Waterproofing of the grill 1 - 100%

Section 5:

  • Reinforcement of pilings, compaction planning and preparation for concreting - 75%

Parking:

  • Reinforcement of concreting monolithic grid 2.1 - 95%

  • Reinforcement of concreting monolithic grid 2.3 - 95%

  • Reinforcement of concreting of the power plate of the parking lot of the 2nd part - 75%

  • Waterproofing of grills 2.1, 2.3 – 100%