20.07.2023
OLEGIV PODIL by DIM is gaining momentum in construction! A new club house in Podil with incredible views of the city panorama.
In July, the following works were performed at the construction site:
Section 3:
Reinforcement of concreting monolithic grid 4.1 - 95%
Reinforcement of concreting monolithic grid 3.1 - 95%
Reinforcement of concreting monolithic grid 4.2 - 95%
Reinforcement of concreting monolithic grid 4.3 - 95%
Waterproofing of grills 4.1, 4.2, 4.3, 3.1 – 100%
Section 4:
Reinforcement of concreting monolithic grid 1 - 80%
Reinforcement of growing piles - 90%
Waterproofing of the grill 1 - 100%
Section 5:
Reinforcement of pilings, compaction planning and preparation for concreting - 75%
Parking:
Reinforcement of concreting monolithic grid 2.1 - 95%
Reinforcement of concreting monolithic grid 2.3 - 95%
Reinforcement of concreting of the power plate of the parking lot of the 2nd part - 75%
Waterproofing of grills 2.1, 2.3 – 100%