24.01.2023
The holidays passed so quickly, and the builders returned to their favorite thing – BUILDING. We are sharing a fresh photo report from the construction site of the New Autograph by DIM for January 2023. Building No. 1, section 1: Installation of parapet covers – 90% Installation of tiles on the fire escape – 100% Building No. 1, section 2: Work on holes for installation of luminaires on the 2nd and 18th floors has been completed – 100% Building No. 1, section 3: Disconnection of control panels for smoke exhaust fan motors on the roof – 100% House No. 2: Metal reinforcement of the HP – 70% Installation of engineering laying of the 1st, 2nd floors (brickwork) – 80% usage – 65% Parking: Monolithic works Parking – 100% Installation of fire water supply – 60% Installation of UDS – 20% Improvement: Installation of reinforced concrete entrance slabs to the parking lot and underground parking lot – 100%