Construction progress for April 2026
01.05.2026
Go back
Sharing the latest news from the construction site for April 2026:
Building №3, Section 1:
- Fire alarm system installation is underway;
- Lobby finishing works continue, suspended ceiling installation with drywall;
- Plumbing works in the lobby – 100%;
- Floor tiling installation – 100%;
- Ceiling installation with cuboid slats in MZK – 100%;
- MZK lighting – 70%;
- Entrance group façade installation and façade lighting – 70%.
Building №3, Section 2:
- Lobby finishing works continue, suspended ceiling installation with drywall;
- Plumbing works in the lobby – 100%;
- Floor tiling installation – 80%;
- Entrance group façade installation and façade lighting – 60%.
Building №3, Section 3:
- Lobby finishing works continue, suspended ceiling installation with drywall – 60%;
- Floor tiling installation – 100%;
- Plumbing works in the lobby – 100%;
- Entrance group façade installation and façade lighting – 60%;
- Ceiling installation with cuboid slats in MZK – 60%.
Works on the construction of the distribution point continue, masonry works completed – 100%.
Waterproofing works of the underground part – 100% and roofing – 90% are in progress.
Works on the installation of the parking floor in building №3 continue – 95%.
Works on landscaping Zone 1 and Zone 2 continue.
Building №4, Section 1:
- Brickwork in the basement – 100%.
Building №4, Sections 4, 5:
- Works on the installation of monolithic parking structures and retaining walls are ongoing.