Sharing the latest news from the construction site for April 2026:

Building №3, Section 1:

  • Fire alarm system installation is underway;
  • Lobby finishing works continue, suspended ceiling installation with drywall;
  • Plumbing works in the lobby – 100%;
  • Floor tiling installation – 100%;
  • Ceiling installation with cuboid slats in MZK – 100%;
  • MZK lighting – 70%;
  • Entrance group façade installation and façade lighting – 70%.

Building №3, Section 2:

  • Lobby finishing works continue, suspended ceiling installation with drywall;
  • Plumbing works in the lobby – 100%;
  • Floor tiling installation – 80%;
  • Entrance group façade installation and façade lighting – 60%.

Building №3, Section 3:

  • Lobby finishing works continue, suspended ceiling installation with drywall – 60%;
  • Floor tiling installation – 100%;
  • Plumbing works in the lobby – 100%;
  • Entrance group façade installation and façade lighting – 60%;
  • Ceiling installation with cuboid slats in MZK – 60%.

Works on the construction of the distribution point continue, masonry works completed – 100%.

Waterproofing works of the underground part – 100% and roofing – 90% are in progress.

Works on the installation of the parking floor in building №3 continue – 95%.

Works on landscaping Zone 1 and Zone 2 continue.

Building №4, Section 1:

  • Brickwork in the basement – 100%.

Building №4, Sections 4, 5:

  • Works on the installation of monolithic parking structures and retaining walls are ongoing.