Metropolis
Construction progress for July 2025

02.08.2025

Go back

Sharing the latest news from the construction site for July:

Building No. 3:

  • sewer pipe installation works 0.4kV - 100%.

Building No. 3, section 1:

  • laying ceramic tile on floors and walls in CWC on the 33rd and 34th floors;
  • continuing decorative plaster application in CWC.

Building No. 3, section 2:

  • decorative plaster application in CWC - 80%;
  • ceramic tile installation on balconies;
  • installation of the last 2 elevators - 100%.

Building No. 3, section 3:

  • decorative plastering of walls (without painting) from the 17th to the 18th floor.
  • Ceramic tile cladding is actively ongoing in CWC, work is being done from the 18th to the 34th floor. Overall completion - 55%.

Parking CWC No. 3:

    waterproofing works on the parking slab continue: bonding, lightweight concrete pouring, membrane installation, drainage membrane and geotextile, protection plate and concrete reinforcement. Completion - 79%.

Building No. 4, section 1:

  • parapet roof works continue;
  • bricklaying of walls from the 32nd to the 33rd floor - 50%;
  • ventilation blocks installation - 100%;
  • window structures installed from the 3rd to the 14th floor and from the 17th to the 22nd floor.

Building No. 4, section 2:

  • staircase construction - 100%;
  • bricklaying of walls on the 2nd, 3rd, 5th and 6th floors in progress.

Building No. 4, section 3:

  • bricklaying of walls from the 1st to the 11th floor - 100%.

Building No. 4, section 5:

  • ventilation blocks installation completed up to the 5th floor - 100%.

Parking CWC No. 4:

  • waterproofing works on piles, pile caps and slab continue;
  • installation of fencing and pile caps, gravel backfill, subballast, reinforcement and concrete laying of the parking slab;
  • works ongoing for the vertical structures of the parking and the slab decking.