Construction progress for July 2025
02.08.2025
Go back
Sharing the latest news from the construction site for July:
Building No. 3:
- sewer pipe installation works 0.4kV - 100%.
Building No. 3, section 1:
- laying ceramic tile on floors and walls in CWC on the 33rd and 34th floors;
- continuing decorative plaster application in CWC.
Building No. 3, section 2:
- decorative plaster application in CWC - 80%;
- ceramic tile installation on balconies;
- installation of the last 2 elevators - 100%.
Building No. 3, section 3:
- decorative plastering of walls (without painting) from the 17th to the 18th floor.
- Ceramic tile cladding is actively ongoing in CWC, work is being done from the 18th to the 34th floor. Overall completion - 55%.
Parking CWC No. 3:
waterproofing works on the parking slab continue: bonding, lightweight concrete pouring, membrane installation, drainage membrane and geotextile, protection plate and concrete reinforcement. Completion - 79%.
Building No. 4, section 1:
- parapet roof works continue;
- bricklaying of walls from the 32nd to the 33rd floor - 50%;
- ventilation blocks installation - 100%;
- window structures installed from the 3rd to the 14th floor and from the 17th to the 22nd floor.
Building No. 4, section 2:
- staircase construction - 100%;
- bricklaying of walls on the 2nd, 3rd, 5th and 6th floors in progress.
Building No. 4, section 3:
- bricklaying of walls from the 1st to the 11th floor - 100%.
Building No. 4, section 5:
- ventilation blocks installation completed up to the 5th floor - 100%.
Parking CWC No. 4:
- waterproofing works on piles, pile caps and slab continue;
- installation of fencing and pile caps, gravel backfill, subballast, reinforcement and concrete laying of the parking slab;
- works ongoing for the vertical structures of the parking and the slab decking.