Construction progress for February 2025
06.03.2025
Go back
We are sharing the latest construction updates for February:
Building No.3, Section 1:
- Installation of heating radiators on the 20th-22nd floors;
- 85% of boilers installed;
- Installation of freight elevators started, 50% completed;
- Common area finishing works have begun;
- Ongoing work on air duct installation and fire protection.
Building No.3, Section 2:
- 90% of balcony railings installed;
- 65% of LMM facade repairs completed;
- Preparatory work for common area finishing is underway.
Building No.3, Section 3:
- 82% of balcony railings installed;
- 40% of LMM facade repairs completed;
- Ongoing work on air duct installation and fire protection;
- Ongoing work on pipeline thermal insulation.
Parking of Building No.3:
- Preparation for the start of roofing works for the parking structure;
- The landscaping concept has been approved, and working documentation is being developed.
Building No.4, Section 1:
- Monolithic frame work on the 33rd floor in progress;
- Stair flights installed in one riser up to the 30th floor inclusive;
- Ventilation blocks installed up to the 23rd floor inclusive.
Building No.4, Section 2:
- Vertical structures and horizontal slab of the 5th floor completed;
- Monolithic frame work on the 6th floor in progress.
Building No.4, Section 3:
- Monolithic frame completed from the 1st to the 15th floor, vertical structures of the 16th floor completed;
- Brickwork of walls from the 2nd to the 7th floor completed – 70%. Work on the 8th floor in progress, 70% done.
Building No.4, Section 5:
- Reinforcement of the 16th floor vertical structures completed, formwork for the horizontal slab installed;
- Stair flight installation completed by 25%;
- Brickwork of walls from the 1st to the 2nd floor completed – 90%. Work in progress on the 3rd-5th floors, 45% completed.
Parking of Building No.4:
- Construction of the tie beam for the retaining wall RM 14 – 90% completed;
- Piling works – 98% completed;
- Excavation and soil removal continue.
External Networks:
- 88% of the relocation of the 10 kV cable line completed;
- A tender process is underway to select a design organization for gas supply design for Building No.4.