Progress of construction in the Metropolis residential complex in July 2022

The Comfort+ residential complex "Metropolis" is located next to the Holosiiv Forest and the VDNG Park. The complex currently includes four buildings, two of which have already been commissioned in the spring of 2021. A large 2-hectare park, a kindergarten, sports and children's playgrounds, as well as a large underground parking lot are planned on the territory.

In July 2022, the following works were performed at the construction site of the "Metropolis"; housing complex:

The second turn

  

Building No. 3, Section 1:

  • Installation of PVC windows - 99%

  • Installation of SPOK-20%

  • Installation of NVF-15%

  • Installation and insertion of the air duct-85%

  • Laying PE pipes and power cable-50%

  • Installation of screed -15%

  • Installation of embedded parts for balcony fencing-40%

  • Masonry of brick mines in apartments - 30%

  

Building No. 3, Section 2:

  • Installation of SPOK-30%

  • Laying PE pipes and power cable -100%

  • Laying of the system T1-T2, water supply B1, T3-60%

  • Installation of sound insulation from the floor slab under the screed-10%

Building No. 3, Section 3:

  • Installation of SPOK-50%

  • Installation of NVF-35%

Railway station parking lot No. 3:

  • Reinforcement and concreting of pylons, parts of the parking lot slab-95%