Construction progress for August 2022

01.09.2022

Go back

The progress of construction in "Metropolis" in September 2022

At the beginning of autumn, the construction of the cozy Comfort+ class complex "Metropolis", located next to the VDNG Park and the Holosiiv Forest, made significant progress.

In September 2022, the following works were performed at the Metropolis construction site:

Building No. 3, Section 1:

  • arrangement of internal brick walls from the 3rd to the 34th floor - 95%;

  • completed works on laying heating pipelines for apartments - 92%;

  • installation of fire valves by apartment - 95%;

  • digitization of the openings of the passage of engineering communications in apartments and MZK - 100%;

  • laying of electrical networks (horizontal) for supplying apartments and boilers, MZK - 80%;

  • placement of NVF - 50%;

  • arrangement of SPOK - 15%;

  • arrangement of the roof - 40%;

  • decoration of the walls of the elevator shaft - 100%.

Building No. 3, Section 2:

  • arrangement of internal brick walls from the 3rd to the 11th floor - 90%;

  • completed works on laying heating pipelines for apartments - 100%;

  • installation of a cement-sand screed floor - 100%;

  • digitization of the openings of the passage of engineering communications in apartments and MZK - 100%;

  • laying of electrical networks (horizontal) for supplying apartments and boilers, MZK - 97%;

  • placement of NVF - 80%;

  • arrangement of SPOK - 90%;

  • arrangement of LMM of the building - 40%;

Building No. 3, Section 3:

  • arrangement of internal brick walls from the 3rd to the 34th floor - 99%;

  • installation of fire valves per apartment - 99%;

  • installation of a cement-sand screed floor - 80%;

  • digitization of the openings of the passage of engineering communications in apartments and MZK - 99%;

  • laying of electrical networks (horizontal) for supplying apartments and boilers, MZK - 99%;

  • placement of NVF - 90%;

  • arrangement of SPOK - 95%;

  • decoration of the walls of the elevator shaft - 100%;

  • laying tiles on the floor in MZK - 30%.

Railway station parking lot No. 3:

  • Arrangement of s/b structures:

  • Pylons - 100%;

  • Floor slab - 100%;

  • Cover plate - 90%;

  • Arrangement of cement-sand screed of technical premises - 100%.

Building No. 4, Section 1:

  • Arrangement of s/b structures:

  • Floor slab 11-12 floor;

  • Reinforcement of floor slabs on the 13th floor;

Railway station parking lot No. 3, 3rd starting point:

1. Pylons - 50%;

2. Floor slab - 95%

3. Cover plate - 50%.

4. Installation of grills - 15%