Construction Progress for January 2025

03.02.2025

Go back

Sharing the latest construction site updates for January:

Building No.3, Parking:

  • Installation of polymer floor coating.

Building No.3, Landscaping:

  • Landscaping of the inner courtyard.

Building No.4:

  • Ongoing work on external power supply networks;
  • Installation of smoke extraction and ventilation systems for the parking lot;
  • Landscaping work in progress;
  • Finishing of technical rooms (wall painting);
  • Roofing installation for the parking lot in the external and internal courtyards;
  • Installation of the ASPG system.

Building No.4, Section 1:

  • Finishing of common areas (from the 3rd to the 13th floors) (integration with fire dampers);
  • Facade finishing (LMM);
  • Masonry work on the 1st and 2nd floors;
  • Installation of smoke extraction and ventilation systems;
  • Installation of PVC structures on the stylobate section;
  • Finishing of technical rooms (wall painting).

Building No.4, Section 2:

  • Facade finishing (LMM);
  • Finishing of common areas from the 3rd to the 13th floors (ceiling painting, drywall ceiling installation);
  • Finishing of technical rooms (wall painting);
  • Masonry work on the 1st and 2nd floors;
  • Ongoing installation of transparent enclosing structures (SPOK).

Building No.4, Section 3:

  • Finishing of common areas from the 3rd to the 13th floors (floor tiling, wall plastering);
  • Installation of smoke extraction and ventilation systems;
  • Installation of transparent enclosing structures (SPOK);
  • Installation of SPZ systems from the 3rd to the 6th floors;
  • Finishing of technical rooms (wall painting).

Building No.5, Section 1:

  • Ongoing construction of walls and partitions on the 11th floor;
  • Installation of the stylobate structure on the 1st floor.

Building No.5, Section 2:

  • Construction of walls and partitions on the 10th floor;
  • Installation of the stylobate structure on the 1st floor.

Building No.5, Section 3:

  • Ongoing installation of ventilation blocks on the 12th and 13th floors;
  • Construction of walls and partitions on the 5th floor.

Building No.5, Parking 1.6 (parking lot adjacent to Section 3):

  • Installation of vertical elements of the monolithic frame on the 1st floor;
  • Roofing installation, slope-forming screed.

Building No.5, Parking 1.5 (parking lot adjacent to Sections 1-2):

  • Installation of horizontal elements of the monolithic frame on the 1st floor.

Building No.6, Section 1:

  • Installation of vertical transportation (passenger elevator);
  • Installation of metal-plastic window structures on the 7th and 8th floors.

Building No.6, Section 2:

  • Installation of vertical transportation (passenger elevator);
  • Facade installation.

Building No.6, Section 3:

  • Facade installation.