Construction Progress for January 2025
03.02.2025
Go back
Sharing the latest construction site updates for January:
Building No.3, Parking:
- Installation of polymer floor coating.
Building No.3, Landscaping:
- Landscaping of the inner courtyard.
Building No.4:
- Ongoing work on external power supply networks;
- Installation of smoke extraction and ventilation systems for the parking lot;
- Landscaping work in progress;
- Finishing of technical rooms (wall painting);
- Roofing installation for the parking lot in the external and internal courtyards;
- Installation of the ASPG system.
Building No.4, Section 1:
- Finishing of common areas (from the 3rd to the 13th floors) (integration with fire dampers);
- Facade finishing (LMM);
- Masonry work on the 1st and 2nd floors;
- Installation of smoke extraction and ventilation systems;
- Installation of PVC structures on the stylobate section;
- Finishing of technical rooms (wall painting).
Building No.4, Section 2:
- Facade finishing (LMM);
- Finishing of common areas from the 3rd to the 13th floors (ceiling painting, drywall ceiling installation);
- Finishing of technical rooms (wall painting);
- Masonry work on the 1st and 2nd floors;
- Ongoing installation of transparent enclosing structures (SPOK).
Building No.4, Section 3:
- Finishing of common areas from the 3rd to the 13th floors (floor tiling, wall plastering);
- Installation of smoke extraction and ventilation systems;
- Installation of transparent enclosing structures (SPOK);
- Installation of SPZ systems from the 3rd to the 6th floors;
- Finishing of technical rooms (wall painting).
Building No.5, Section 1:
- Ongoing construction of walls and partitions on the 11th floor;
- Installation of the stylobate structure on the 1st floor.
Building No.5, Section 2:
- Construction of walls and partitions on the 10th floor;
- Installation of the stylobate structure on the 1st floor.
Building No.5, Section 3:
- Ongoing installation of ventilation blocks on the 12th and 13th floors;
- Construction of walls and partitions on the 5th floor.
Building No.5, Parking 1.6 (parking lot adjacent to Section 3):
- Installation of vertical elements of the monolithic frame on the 1st floor;
- Roofing installation, slope-forming screed.
Building No.5, Parking 1.5 (parking lot adjacent to Sections 1-2):
- Installation of horizontal elements of the monolithic frame on the 1st floor.
Building No.6, Section 1:
- Installation of vertical transportation (passenger elevator);
- Installation of metal-plastic window structures on the 7th and 8th floors.
Building No.6, Section 2:
- Installation of vertical transportation (passenger elevator);
- Facade installation.
Building No.6, Section 3:
- Facade installation.