LUCKY LAND eco-city is actively growing! Construction work is in full swing, we are erecting facades, laying engineering, finishing works, preparing for commissioning of the 3rd building!

LUCKY LAND is so unique, located in a unique location, next to a majestic forest and all the necessary infrastructure. Progressive technological solutions, individual heating, designer lobbies, the highest quality materials, landscaping designed to the smallest detail - all this makes life in LUCKY LAND comfortable and cozy.

We thank the brave Armed Forces, our builders for the opportunity to build in such difficult times for Ukraine. We thank our esteemed investors for their trust and timely payment of installments, each of you makes a significant contribution to the construction of LUCKY LAND.

We share the October report on the construction of the best LUCKY LAND eco-complex:

Building No. 3, Section 1:

  • work on the installation of external networks B1, K1, K2 is being carried out;
  • work on the installation of external ETR networks is being carried out;
  • arrangement of equipment of basement premises;
  • arrangement of equipment input group;
  • work on the installation of external networks B1, K1, K2 is being carried out;
  • work on the installation of external ETR networks is being carried out;
  • arrangement of equipment of basement premises;
  • arranging the equipment of the entrance group;
  • installation of pumping equipment and water metering unit;
  • installation of ceramic tiles on cold transitions.

Building No. 3, Section 2:

  • arrangement of equipment of basement premises;
  • installation of ceramic tiles on cold transitions.

Building No. 3, Section 3:

  • arrangement of equipment of basement premises;
  • arrangement of facades;
  • installation of ceramic tiles on cold transitions.

Building No. 4, Section 1:

  • arrangement of facades;
  • work on the decoration of technical superstructures and ventilation shafts on the roof is being carried out;
  • installation of elevator equipment.

Building No. 4, Section 2:

  • arrangement of facades;
  • finishing works on technical superstructures and ventilation shafts on the roof are being carried out.

Building No. 4, Section 3:

  • finishing works on technical superstructures and ventilation shafts on the roof are being carried out.

Building No. 6, Section 2:

  • bricklaying of ventilation shafts on the roof is carried out;
  • waterproofing of the roof is carried out.

Building No. 6, Section 1:

  • bricklaying work on the 8th floor is underway.