A136 Highlight Tower
Construction progress for June 2022

15.06.2022

Go back

Construction progress at BFC A136 Highlight Tower for June 2022

The A136 Highlight Tower complex is located in the very heart of the capital at the intersection of the city's business and cultural arteries. The first premium class living in Ukraine is planned on the fifth floor of the elite BFK A136 Highlight Tower. Also, all residents of the building will have access to a co-working space, a cinema, a game room, an open terrace with a cafe, where you can enjoy the panorama of the entire city in the morning light or the rays of the evening sun.

In June 2022, the following works were performed at the construction site of BFC A136 Highlight Tower:

  • The floor slab of the 16th floor has been installed - 42%;

  • Brickwork from -2 to 13 floors - 67%;

  • Plumbing works from -2nd to 13th floor were completed - 38%;

  • Completed electrical installation work from -2 to 13 floors - 35%;

  • The smoke removal system of floors -2 and -1 was completed - 45%;

  • The ventilation system of floors -2 and -1 - 38% was completed;

The following works are performed:

  • Brickwork of walls from the 10th to the 13th floor;

  • Plumbing works on the installation of water pipes, sewerage and drainage systems;

  • Electrical works from -2nd to 13th floor;

  • Installation of smoke removal and fire extinguishing from -2nd to 5th floor;

  • Installation of ventilation systems on -2 and -1 floors;

  • Plastering works on -2 and -1 floors;

  • Installation of ventilation ducts and staircases.