Construction progress for July 2022
20.07.2022
Construction progress at BFC A136 Highlight Tower July 2022
The A136 Highlight Tower complex is located in the very heart of the capital at the intersection of the city's business and cultural arteries. The first premium class living in Ukraine is planned on the fifth floor of the elite BFK A136 Highlight Tower. Also, all residents of the building will have access to a co-working space, a cinema, a game room, an open terrace with a cafe, where you can enjoy the panorama of the entire city in the morning light or the rays of the evening sun.
In July 2022, the following works were performed at the construction site of BFC A136 Highlight Tower:
The floor slab of the 17th floor has been installed - 60%;
Vertical elements of walls and columns on the 17th floor have been installed - 100%;
Vertical elements of walls and columns on the 18th floor are arranged - 10%;
Brickwork from -2 to 15th floor was completed - 65%;
Plumbing works from -2nd to 13th floor were completed - 35%;
Completed electrical installation work from -2 to 13th floor - 30%;
The smoke removal system of floors -2 and -1 was completed - 40%;
The ventilation system of floors -2 and -1 was completed - 30%;
The automatic fire extinguishing system was implemented from -2 to 4 floors - 70%;
Plastering of technical premises and MZK -2 and -1 floors was completed - 45%;
68% of window structures from the 6th to the 11th floor have been installed;
65% of the double-glazed windows of the window structures from the 6th to the 11th floor have been installed;
75% of SPOK stained-glass systems have been installed from the 6th to the 15th floor;
60% of the double-glazed windows of the stained-glass systems from the 6th to the 15th floor have been installed;
The 2, 3, 4, 5 floors are covered with a stylobate roof - 30%.
10% of the cladding of the stylobate facade (insulation and subsystem) has been arranged.
The following works are performed:
Concreting of vertical elements on the 18th floor;
Preparation for concreting the floor slab of the 17th floor;
Brickwork of walls from the 10th to the 15th floor;
Installation of window systems from the 6th to the 15th floor;
Installation of stained glass systems from the 6th to the 15th floor;
Preparatory work has begun on the installation of office elevators from the 1st to the 5th floor;
Installation of ventilation ducts and staircases.
Installation of subsystems for facing the stylobate with natural stone.